Mountain Vista United Methodist Church
Daily Construction Diary
July 31, 2001

 

Report for Tuesday, July 31, 2001

We had a five man crew working on the steel frame today and made good progress. The metal studs and fasteners for the walls were delivered today and the concrete approach and remaining curb on our driveway were poured jointly by our crew and the West Jordan crew. The cooperation on this part of the project has been very good.

We met with the utilities inspector today and worked out an acceptable approach to working around the utility conflicts during installation of the sewer and water connections. We will have our plans complete when we are able to finally locate a three phase buried electrical transmission set of lines.

Photos today show the roof panels ready for installation, the metal studs being delivered and still on the truck, and the erection crew working on the roof purlins and braces.


| Home | Worship | Sunday School | Youth | Music Ministry | Special Ministries | Prayer Room | Construction Diary | Committees | Joyful Sound | Newsletter | Calendar | Core Values |