Friday, August 17, 2001

More framing completed inside today. The corridor, Photo A, and storage spaces in sanctuary corners, Photos B and C, are essentially complete. We have started installation of the flexible conduit for the wiring in the walls, Photo D.

Trenches for sprinkler installation, Photos E, F, and G, were dug today and the excavation contractor excavated for the water meter vault and connection. The roof work is now nearly complete.

Bob Lindsay finished the trench for the telephone line around the easterly perimeter and the telephone company was notified the trench is available to them.